SATORI SITE UPDATE /🏗️
Excavation continues to move steadily across the site. With bulk excavation almost complete, our crews are beginning detailed excavation and layout work for upcoming strip and pad footings.
Once these areas are prepared, mechanical sumps (pic 1) will be installed as part of the site’s drainage infrastructure.
Along the perimeter, shotcrete installation is nearing completion! The remaining wire mesh reinforcement has been staged on site and will be incorporated into the final sections as work progresses.
Every week brings another visible step forward as Satori continues to take shape 🪨🌸