06/11/2026
🌱⚡ Another exciting milestone reached! ⚡🌱
The MCH Solutions team has now completed the foundation, cable trenching, ducting and underground infrastructure for Scotland's first Norhybrid EnergyBlade 3.6 vertical-axis wind turbine.
With the reinforced concrete foundation poured and cured before winter conditions set in, the project is now ready for the next stage. Meanwhile, our partners at Norhybrid are manufacturing the turbine in Norway ahead of an anticipated installation in Q1 2027.
One of the most interesting aspects of this project is that the foundation has been designed to sit slightly below ground level, allowing it to be covered with topsoil so livestock can graze right up to the turbine base.
A huge thank you to our customer and everyone involved. The team thoroughly enjoyed working on this fantastic site and witnessing some spectacular Scottish sunrises along the way.
📸 Photos below of the works and the amazing scenery we've been lucky enough to enjoy.